How much does an electrical connection cost in 2026 (real prices + cost factors)
How much does an electrical connection cost in 2026
If you want to run power from the pole to your house, plot or building site, the total cost falls into two broad categories: the connection works (labour + materials, carried out by an ANRE-certified company such as SUN WATT SRL) and the connection fee (the charge paid to the distribution operator, Retele Electrice Romania S.A.).
For the works, guideline prices in 2026 start from 1,800 lei for single-phase and from 2,900 lei for three-phase. The connection fee is calculated separately by the operator and officially communicated to you through the Technical Connection Approval (ATR), depending on the power requested and the type of connection (bransament).
In this guide you will find a table of prices by connection type, a detailed explanation of the factors that influence the price, and the steps that take you from application to energisation (punere sub tensiune).
Guideline price table for electrical connections 2026
The amounts below represent labour + materials, excluding the distribution operator’s charges. The final, personalised price is confirmed after an assessment of your specific situation.
| Connection type | Guideline price (from) | Recommended for |
|---|---|---|
| Single-phase (230 V) | 1,800 lei | Homes with low/medium consumption, studio flats, outbuildings |
| Three-phase (400 V) | 2,900 lei | Large houses, high-power consumers, workshops |
| Underground | 3,500 lei | Areas with no nearby pole, aesthetics, new neighbourhoods |
| Temporary site connection | 2,200 lei | Site setup, buildings under construction |
| DIU dossier | 1,200 lei | Utilisation Installation Dossier (proof of internal installation) for the meter |
| Connection dossier / project | 900 lei | Documentation required to submit the application to the operator |
These values are indicative. For an exact estimate, use the connection cost calculator or consult the full prices page.
How much does it cost to run power from the pole?
The question “how much does it cost to run power from the pole” does not have a single answer, because it depends on the distance between the network pole and the delimitation point (usually the connection cabinet (firida de bransament) mounted at the property boundary). The greater the distance and the more complicated the route, the higher the labour and material costs (conductor, brackets, accessories).
Broadly speaking, a standard single-phase overhead connection, with the pole close to the property, falls within the starting price of 1,800 lei for the works. If an additional pole, a long route or an underground connection is required, the cost increases accordingly.
The factors that influence the price of a connection
The final price of an electrical connection depends on several factors. Here are the most important ones.
1. The type of connection: single-phase vs three-phase
The price difference between single-phase and three-phase is one of the most sought-after pieces of information.
- Single-phase (230 V) – from 1,800 lei. Sufficient for an ordinary home, with approved power usually up to ~11 kW. Simpler to carry out and cheaper.
- Three-phase (400 V) – from 2,900 lei. Required when you have high-power consumers (heat pump, high-capacity electric hob cooker, workshop, car charging station). More materials and labour, hence a higher price.
If you are not sure which suits you, see the detailed comparison on the three-phase connection page.
2. The power requested (kW)
The approved power influences both the cross-section of the cables and the sizing of the equipment, as well as the connection fee charged by the operator. Higher power means more robust materials and, frequently, a higher connection fee.
3. The distance to the distribution network
The length of the route from the pole/network to the connection cabinet matters directly. Long distances may require additional poles or greater cable lengths, which increases the total cost.
4. Overhead vs underground
- Overhead – the most economical option, recommended when there is a pole nearby.
- Underground – from 3,500 lei, more expensive because of the excavation, protective conduit, armoured cable and ground reinstatement. Advantages: aesthetics, durability, no overhead cables.
5. The connection fee through the ATR
This is the cost paid to the operator Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel). The value is NOT set by the contractor, but by the operator, and you receive it officially in the Technical Connection Approval (ATR). The fee depends on the power, the type of connection and the technical solution chosen by the operator. That is why you only know the full final price once the ATR has been issued.
What the total cost is made up of: works + operator charges
To understand the budget clearly, divide the cost into two:
- The connection works (what you pay the ANRE-certified company) – design, materials, labour, cabinet installation, DIU dossier. The prices in the table above fall here.
- The connection fee (what you pay the operator) – set through the ATR, based on the power and the technical solution.
To these is added, where applicable, the cost of the connection dossier (from 900 lei) and the DIU dossier (from 1,200 lei), documents that are mandatory in the connection process.
The steps of the grid connection process
The process from idea to power in the socket has 6 clear stages:
- The connection application + documents – you submit the dossier to the operator (land/building documents, plan, technical data).
- The Technical Connection Approval (ATR) – the operator sets the solution and the connection fee.
- The connection contract + payment of the fee – you sign and pay the fee to the operator.
- Design + execution – the ANRE-certified company prepares the project and carries out the actual works.
- The DIU dossier – the Utilisation Installation Dossier, mandatory for installing the meter. Details on the DIU dossier page.
- Installing the meter + energisation – the operator installs the meter and powers up the installation.
Why choose SUN WATT SRL
SUN WATT SRL is the ANRE-certified company (execution + design) specialising in electrical connections in Bucharest, Ilfov and Giurgiu, and for DIU dossiers we work throughout the country. We manage the entire process for you, from the connection application to energisation, with transparent prices and clear communication.
Want to know exactly what it will cost you? Get a quick estimate with the cost calculator, consult the full list of prices or write to us directly via the contact page. You can call us any time at 0733 097 440.