How much does an electrical connection cost in 2026 (real prices + cost factors)

In short: In 2026, an electrical connection (bransament) costs, as a guideline, from 1,800 lei for single-phase, from 2,900 lei for three-phase and from 3,500 lei for the underground option (labour + materials, excluding the operator's fee). To these amounts is added the connection fee charged by Retele Electrice Romania S.A., the exact value of which appears in the Technical Connection Approval (ATR). For a personalised budget, use the cost calculator or request a quote at 0733 097 440.

How much does an electrical connection cost in 2026

If you want to run power from the pole to your house, plot or building site, the total cost falls into two broad categories: the connection works (labour + materials, carried out by an ANRE-certified company such as SUN WATT SRL) and the connection fee (the charge paid to the distribution operator, Retele Electrice Romania S.A.).

For the works, guideline prices in 2026 start from 1,800 lei for single-phase and from 2,900 lei for three-phase. The connection fee is calculated separately by the operator and officially communicated to you through the Technical Connection Approval (ATR), depending on the power requested and the type of connection (bransament).

In this guide you will find a table of prices by connection type, a detailed explanation of the factors that influence the price, and the steps that take you from application to energisation (punere sub tensiune).

Guideline price table for electrical connections 2026

The amounts below represent labour + materials, excluding the distribution operator’s charges. The final, personalised price is confirmed after an assessment of your specific situation.

Connection typeGuideline price (from)Recommended for
Single-phase (230 V)1,800 leiHomes with low/medium consumption, studio flats, outbuildings
Three-phase (400 V)2,900 leiLarge houses, high-power consumers, workshops
Underground3,500 leiAreas with no nearby pole, aesthetics, new neighbourhoods
Temporary site connection2,200 leiSite setup, buildings under construction
DIU dossier1,200 leiUtilisation Installation Dossier (proof of internal installation) for the meter
Connection dossier / project900 leiDocumentation required to submit the application to the operator

These values are indicative. For an exact estimate, use the connection cost calculator or consult the full prices page.

How much does it cost to run power from the pole?

The question “how much does it cost to run power from the pole” does not have a single answer, because it depends on the distance between the network pole and the delimitation point (usually the connection cabinet (firida de bransament) mounted at the property boundary). The greater the distance and the more complicated the route, the higher the labour and material costs (conductor, brackets, accessories).

Broadly speaking, a standard single-phase overhead connection, with the pole close to the property, falls within the starting price of 1,800 lei for the works. If an additional pole, a long route or an underground connection is required, the cost increases accordingly.

The factors that influence the price of a connection

The final price of an electrical connection depends on several factors. Here are the most important ones.

1. The type of connection: single-phase vs three-phase

The price difference between single-phase and three-phase is one of the most sought-after pieces of information.

  • Single-phase (230 V) – from 1,800 lei. Sufficient for an ordinary home, with approved power usually up to ~11 kW. Simpler to carry out and cheaper.
  • Three-phase (400 V) – from 2,900 lei. Required when you have high-power consumers (heat pump, high-capacity electric hob cooker, workshop, car charging station). More materials and labour, hence a higher price.

If you are not sure which suits you, see the detailed comparison on the three-phase connection page.

2. The power requested (kW)

The approved power influences both the cross-section of the cables and the sizing of the equipment, as well as the connection fee charged by the operator. Higher power means more robust materials and, frequently, a higher connection fee.

3. The distance to the distribution network

The length of the route from the pole/network to the connection cabinet matters directly. Long distances may require additional poles or greater cable lengths, which increases the total cost.

4. Overhead vs underground

  • Overhead – the most economical option, recommended when there is a pole nearby.
  • Underground – from 3,500 lei, more expensive because of the excavation, protective conduit, armoured cable and ground reinstatement. Advantages: aesthetics, durability, no overhead cables.

5. The connection fee through the ATR

This is the cost paid to the operator Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel). The value is NOT set by the contractor, but by the operator, and you receive it officially in the Technical Connection Approval (ATR). The fee depends on the power, the type of connection and the technical solution chosen by the operator. That is why you only know the full final price once the ATR has been issued.

What the total cost is made up of: works + operator charges

To understand the budget clearly, divide the cost into two:

  1. The connection works (what you pay the ANRE-certified company) – design, materials, labour, cabinet installation, DIU dossier. The prices in the table above fall here.
  2. The connection fee (what you pay the operator) – set through the ATR, based on the power and the technical solution.

To these is added, where applicable, the cost of the connection dossier (from 900 lei) and the DIU dossier (from 1,200 lei), documents that are mandatory in the connection process.

The steps of the grid connection process

The process from idea to power in the socket has 6 clear stages:

  1. The connection application + documents – you submit the dossier to the operator (land/building documents, plan, technical data).
  2. The Technical Connection Approval (ATR) – the operator sets the solution and the connection fee.
  3. The connection contract + payment of the fee – you sign and pay the fee to the operator.
  4. Design + execution – the ANRE-certified company prepares the project and carries out the actual works.
  5. The DIU dossier – the Utilisation Installation Dossier, mandatory for installing the meter. Details on the DIU dossier page.
  6. Installing the meter + energisation – the operator installs the meter and powers up the installation.

Why choose SUN WATT SRL

SUN WATT SRL is the ANRE-certified company (execution + design) specialising in electrical connections in Bucharest, Ilfov and Giurgiu, and for DIU dossiers we work throughout the country. We manage the entire process for you, from the connection application to energisation, with transparent prices and clear communication.

Want to know exactly what it will cost you? Get a quick estimate with the cost calculator, consult the full list of prices or write to us directly via the contact page. You can call us any time at 0733 097 440.

Frequently asked questions

How much does a single-phase electrical connection cost in 2026?

A single-phase electrical connection costs, as a guideline, from 1,800 lei (labour + materials), excluding the operator's connection fee. The final price depends on the distance to the pole, the power requested and the technical solution in the ATR.

What is the price difference between a single-phase and a three-phase connection?

A single-phase connection starts from 1,800 lei, and a three-phase one from 2,900 lei. Three-phase is more expensive because it requires more materials and labour, being recommended for high-power consumers (heat pump, workshop, car charging station).

How much does it cost to run power from the pole to the house?

The cost depends on the distance between the pole and the property and on the type of connection. A standard single-phase overhead connection, with the pole nearby, starts from 1,800 lei for the works. If an additional pole or the underground option (from 3,500 lei) is needed, the price increases.

What is the connection fee and who sets it?

The connection fee (charge) is the amount paid to the operator Retele Electrice Romania S.A. for connection to the network. It is not set by the contractor, but by the operator, through the Technical Connection Approval (ATR), depending on the power and the technical solution chosen.

Why can't I find out the final price of the connection from the start?

We can quickly estimate the price of the works (labour + materials), but the total cost also includes the operator's connection fee, which is calculated and officially communicated only through the ATR. That is why you know the full, definitive price after the Technical Connection Approval has been issued.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp