Grid Connection to PPC / Distributie Energie Muntenia (formerly Enel): a step-by-step guide

In short: "Enel connection" is now handled by **Retele Electrice Romania S.A.** (formerly E-Distributie Muntenia / Enel, part of the PPC group), the distribution operator for Bucharest, Ilfov and Giurgiu. The process has 6 stages: submitting the grid connection (racordare) dossier, issuing the ATR (Technical Connection Approval / aviz tehnic de racordare), signing the connection contract, carrying out the works, energisation (punere sub tensiune) and the supply contract. At SUN WATT SRL (ANRE-certified for execution + design), indicative prices start from **1,800 lei** for a single-phase connection (bransament, ~11 kW), **2,900 lei** three-phase (400V) and **3,500 lei** underground; dossier + connection design from **900 lei**, ATR assistance from **350 lei**. The final price is set by the ATR.

“Enel connection” is still the term used by most customers in the Bucharest - Ilfov - Giurgiu area, yet the distribution operator no longer goes by this name. Today, connection to the low-voltage grid is handled by Retele Electrice Romania S.A., the current name of the former E-Distributie Muntenia (previously Enel Distributie Muntenia), a company that is part of the PPC (Public Power Corporation) group. Regardless of the name, the administrative steps remain regulated by ANRE and are the same for any distribution operator.

This guide explains, step by step, how to obtain your connection (bransament): what the connection dossier contains, what the ATR is and why it matters, what processing times you can estimate, and where an ANRE-certified company such as SUN WATT SRL can step in to shorten the process.

Who the operator is today: from Enel to PPC

The chain of renamings has caused a lot of confusion, so it is worth clarifying:

  • Enel Distributie MunteniaE-Distributie MunteniaRetele Electrice Romania S.A. (the current distribution operator / OD, part of the PPC group).
  • Energy supply (your electricity bill) is separate from distribution. You can have a supply contract with any provider on the open market, but the physical connection to the grid is handled exclusively by the distribution operator in your area.

For Bucharest, Ilfov and part of Giurgiu, the distribution operator is Retele Electrice Romania (formerly Enel). This is where the connection dossier is submitted and from where the ATR is issued.

What “connection” means and which type of connection you need

A grid connection (racordare) is the set of works through which your property is connected to the public distribution grid. Depending on the power requirement and the type of building, you choose:

  • Single-phase connection – the usual solution for homes, with approved power typically around 11 kW. Details and price.
  • Three-phase connection – for larger consumers, houses with heat pumps, workshops, 400V voltage.
  • Underground connection – when the grid or urban planning requirements call for the cable to be laid underground.
  • Temporary site connection – to supply power during the construction of a building.

If you are not sure what power to request, use the connection cost calculator or request an assessment via contact.

The steps of the connection dossier with PPC / Retele Electrice Romania

The connection process follows a clear, regulated sequence. Here is what each stage involves:

1. Preparing and submitting the connection dossier

The connection request is submitted to the distribution operator together with supporting documents: identity document / company details, proof of ownership of the property, urban planning certificate (where applicable), site plan and location plan, a description of the consumers and the requested power. An ANRE-certified company draws up the connection dossier and design so that it is accepted on the first attempt.

2. Issuing the Technical Connection Approval (ATR)

The ATR is the key document: it establishes the technical connection solution, the approved power, the delimitation point and the connection tariff. In practice, the final price of the connection is confirmed through the ATR. See our ATR assistance and acquisition service.

3. Signing the connection contract

After the ATR is accepted and the connection tariff is paid, the connection contract is signed with the operator.

4. Carrying out the connection works

The actual work (installing the connection cabinet/BMPT, laying the cable, the meter) is performed by a certified contractor. SUN WATT carries out overhead and underground connections in Bucharest, Ilfov and Giurgiu.

5. Energisation (PST)

After checks and acceptance, the operator energises the connection.

6. The supply contract

With the connection in operation, you sign the supply contract with your chosen provider and begin consumption.

Table: connection stages, what you do and indicative timelines

StageWhat happensWho actsIndicative time*
1. Connection dossierDrawing up and submitting documentationClient + certified company1-2 weeks (preparation)
2. Issuing ATRTechnical solution + connection tariffDistribution operator (PPC)~30 working days
3. Connection contractPaying the tariff, signingClient + operatora few days
4. Connection worksInstalling cabinet, cable, meterANRE-certified contractordays - a few weeks
5. EnergisationChecks, acceptance, PSTDistribution operatorafter acceptance
6. Supply contractActivating consumptionClient + providera few days

*Times are indicative; exact deadlines depend on the complexity of the work, the area and the operator’s workload. The legal processing deadlines are those set out in ANRE regulations.

Indicative costs for connection in Bucharest / Ilfov / Giurgiu

The prices below are indicative and are confirmed finally through the ATR (which includes the operator’s connection tariff). For a personalised quote, see the prices page.

ServiceIndicative price (from)
Single-phase connection (~11 kW)1,800 lei
Three-phase connection (400V)2,900 lei
Underground connection3,500 lei
Temporary site connection2,200 lei
Connection dossier + design900 lei
ATR assistance350 lei
DIU (Installation/Conformity Declaration)1,200 lei
Power upgrade (spor de putere)350 lei
Earthing connection900 lei
PRAM (testing)250 lei

Why work with an ANRE-certified company

A grid connection involves technical terms, compliant documentation and interaction with the distribution operator. An ANRE-certified company for execution and design reduces the risk of the dossier being rejected and shortens the dead time between stages. SUN WATT SRL offers:

In short: you tell us what power you need and where, and we take the dossier from the request all the way to energisation.

Conclusion

Although customers still ask for an “Enel connection”, the current operator for Bucharest, Ilfov and Giurgiu is Retele Electrice Romania S.A. (PPC). The process has 6 stages, with the ATR as the decisive point for the technical solution and the final price. With an ANRE-certified company, the dossier flows faster and the costs are clear from the outset.

Call 0733 097 440 or write to us from the contact page for a free assessment of your connection.

Frequently asked questions

Does Enel still exist for connections in Bucharest and Ilfov?

Not under that name. Enel Distributie Muntenia became E-Distributie Muntenia, and the distribution operator is now called Retele Electrice Romania S.A., part of the PPC group. Functionally, it is the same company that manages connections in Bucharest, Ilfov and Giurgiu; only the name has changed.

What is the ATR and why is it so important?

The ATR (Technical Connection Approval / aviz tehnic de racordare) is the document issued by the distribution operator that establishes the technical solution, the approved power, the delimitation point and the connection tariff. In practice, the final price of the connection is confirmed through the ATR. SUN WATT provides ATR assistance from 350 lei.

How long does connection to PPC / Retele Electrice Romania take?

The times are indicative and depend on the area and complexity. Preparing the dossier takes 1-2 weeks, issuing the ATR around 30 working days, followed by the connection contract, carrying out the works and energisation. The exact deadlines are those regulated by ANRE.

How much does a single-phase or three-phase connection cost?

Indicatively, a single-phase connection (approx. 11 kW) starts from 1,800 lei, a three-phase one (400V) from 2,900 lei, and an underground one from 3,500 lei. Prices are confirmed finally through the ATR, which includes the operator's connection tariff. See the prices page for details.

Can I prepare the connection dossier myself, or do I need a certified company?

You can submit the request yourself, but the connection dossier and design must be drawn up in accordance with the regulations, and the works must be carried out by an ANRE-certified contractor. A certified company such as SUN WATT SRL reduces the risk of rejection and shortens the timelines. The dossier + design start from 900 lei.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp