Electrical connection and rising mains in apartment blocks: what they involve and how much they cost

In short: In an apartment block, the electrical connection (bransament) — running from the Retele Electrice Romania grid to the general metering block — is complemented by the rising mains (coloane electrice montante) that distribute power across stairwells and floors, plus the floor cabinets and the separation of consumption per apartment. A three-phase 400V connection starts from 2,900 lei, while an underground one starts from 3,500 lei; rising-main works are priced according to the number of levels and apartments, with the final price set through the ATR (Technical Connection Approval). The grid connection dossier and design start from 900 lei.

In a multi-dwelling building, the power supply does not come down to a single cable: there is an apartment-block electrical connection (bransament) that brings power from the grid of operator Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel, part of the PPC group) up to the general metering and protection block, and from there the rising mains (coloane electrice montante) distribute the current vertically, towards the floor cabinets and then towards each apartment’s meter. A three-phase 400V connection starts from 2,900 lei, the underground version from 3,500 lei, and the dossier with grid connection design from 900 lei. The exact cost of the rising mains depends on the number of stairwells, levels and apartments, and is confirmed through the ATR (Technical Connection Approval / Avizul Tehnic de Racordare).

What an apartment-block connection is and how it differs from an individual one

For a detached house, the connection links the grid to a single single-phase metering block (~11 kW) or three-phase one (400V). For a residential block, the layout is more extensive:

  • The connection (bransament) itself brings power from the operator’s pole or transformer substation up to the building’s general metering and protection cabinet (firida / BMPG). For a high combined consumption, this is almost always three-phase.
  • The rising main (coloana electrica montanta) is the vertical route (cables + protective conduits) that runs from the general cabinet and climbs the stairwell, supplying one floor cabinet (firida de etaj) at each level.
  • The individual columns (the branch lines) run from the floor cabinet to the consumer unit and meter of each apartment, ensuring the separation of consumption per subscriber.

In practice, the connection is the “artery” that enters the building, while the rising mains are the “internal distribution network” that carries power up to each consumer’s door.

The rising main: its role and components

The rising main is the backbone of the block’s electrical installation. A rising main that is correctly sized and installed in line with the standards ensures both safety and the ability to add power upgrades (sporuri de putere) without reworking the entire route.

The main components

  • The connection cabinet (firida de bransament) / BMPG – the demarcation point between the operator’s grid and the building’s installation, with general protective devices.
  • The rising-main cable – cross-section sized according to the total power of the stairwell and the number of apartments.
  • The floor cabinets (distribution boxes) – at each level, from which the branches run off towards the apartments.
  • The individual columns and metering blocks – the meter and protective device of each apartment, the basis of consumption separation.
  • The protective conduit and the earthing system (earth electrode / priza de pamant) – mandatory for the protection of people and equipment.

When work is carried out on the rising mains

Work on the rising mains (coloane electrice) typically arises in the following situations:

  1. New block – the full installation of the rising mains and floor cabinets.
  2. Refurbishment / modernisation – old aluminium rising mains, undersized or degraded, that can no longer cope with current consumption (electric boilers, induction hobs, EV charging).
  3. Separation of consumption – when moving from shared metering to individual metering per apartment.
  4. Power upgrade (spor de putere) at stairwell or building level, which requires the rising main to be reassessed.

You will find details about the installation work on the rising mains page.

Separation of consumption per apartment

Separation of consumption means that each apartment has its own meter and its own individual connection (a column branched off from the floor cabinet), with a separate contract with the supplier. The advantages are clear: accurate billing, with no shared apportionments, and independent protective devices for each dwelling.

The process generally involves: a grid connection dossier, a design, obtaining the ATR for the new layout, the installation of the rising mains and metering blocks, then the fitting of the meters by the operator. For consumers with higher requirements, the usual solution is a three-phase connection 400V per apartment or for the stairwell as a whole.

How much it costs: indicative prices

The prices below are indicative, for works in Bucharest, Ilfov and Giurgiu. The total cost of rising-main works in a block is calculated according to the number of levels, apartments and the length of the routes, while the final power and technical solution are set through the ATR.

ServiceIndicative price (from)Notes
Single-phase connection1,800 lei~11 kW, for small / individual spaces
Three-phase connection2,900 lei400V, recommended for high consumption
Underground connection3,500 leiBuried route, neat and protected
Temporary site connection2,200 leiFor the construction period
Dossier + grid connection design900 leiTechnical documentation
ATR assistance350 leiSupport in dealings with the operator
DIU (installer’s declaration)1,200 leiValid nationally
Power upgrade350 leiPer request / stairwell
Earth electrode900 leiMandatory for safety
PRAM (testing)250 leiTest certificate

For a calculation closer to your situation, use the connection cost calculator or check the full list of prices.

Note: for rising mains, the price is not fixed per building — it reflects the labour, the materials (cable, conduits, cabinets) and the complexity of the route. Request an on-site assessment.

The steps of an apartment-block connection and rising-main project

  1. Assessment and consultancy – establishing the power required (per apartment and combined) and the technical solution.
  2. Grid connection dossier and design – the technical documentation submitted to Retele Electrice Romania.
  3. Obtaining the ATR – the approval that confirms the solution and the approved power; this is where the final connection price is set.
  4. Carrying out the works – connection, rising mains, floor cabinets, individual columns, earth electrode.
  5. PRAM testing and DIU – test certificates and the authorised installer’s declaration.
  6. Fitting the meters and energisation (punere sub tensiune) – carried out by the operator after handover.

Why an ANRE-certified company

Apartment-block electrical connection and rising-main works must be carried out by an ANRE-certified company for both installation and design, so that they are accepted by the distribution operator. SUN WATT SRL (bransam.ro) covers the entire process: design, grid connection dossier, ATR assistance, installation and testing, with a DIU valid nationally.

Do you have a new block, a rising-main refurbishment or a separation of consumption in the pipeline? Write to us or call 0733 097 440 and we will prepare a quote based on your building’s layout. See also the contact page.

Frequently asked questions

What is the difference between the electrical connection and the rising main in an apartment block?

The connection (bransament) brings power from the Retele Electrice Romania grid up to the building's general metering cabinet (block). The rising main (coloana electrica montanta) is the vertical route that distributes power onwards, from the general cabinet to the floor cabinets and then to the meter of each apartment. The connection is the entry artery, while the rising mains are the internal distribution network.

How much do the rising mains in an apartment block cost?

There is no fixed price per building: the cost depends on the number of stairwells, levels and apartments, on the length of the routes and on the materials used (cable, conduits, cabinets). A three-phase connection starts from 2,900 lei, while the underground version starts from 3,500 lei. For rising mains we recommend an on-site assessment, with the final price confirmed through the ATR.

What does separation of consumption per apartment mean?

It means that each apartment has its own meter and individual connection (a column branched off from the floor cabinet), with a separate contract with the supplier. This way, billing is accurate, with no shared apportionments, and the protective devices are independent for each dwelling. The process includes a grid connection dossier, a design, the ATR and the installation of the rising mains and metering blocks.

When should old rising mains be replaced?

Usually when the rising mains are made of aluminium, undersized or degraded and can no longer cope with current consumption (electric boilers, induction hobs, EV charging). Replacement is also recommended during a block's refurbishment, when separating consumption, or when a power upgrade is requested that requires the rising main to be reassessed.

Who can carry out connection and rising-main works in an apartment block?

Only a company certified by ANRE for both installation and design, so that the work is accepted by the distribution operator. SUN WATT SRL (bransam.ro) covers the entire process — design, grid connection dossier, ATR assistance, installation, PRAM and a DIU valid nationally — in Bucharest, Ilfov and Giurgiu. Details on 0733 097 440.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp