Casa Verde solar panels and grid connection: what to do after installation (2026 guide)

In short: Solar panels installed through the Casa Verde programme do not inject energy into the grid or offset your bill until you are officially connected as a prosumer (prosumator). After the AFM-funded installation, you still need a connection dossier, the Technical Connection Approval (ATR) from Rețele Electrice România S.A., a bidirectional meter fitted by the operator and the connection certificate (certificat de racordare), followed by a prosumer contract with your supplier. The Casa Verde installer mounts the equipment; the grid connection is a separate process. SUN WATT (ANRE no. 19761) handles this part in Bucharest, Ilfov and Giurgiu: 0733 097 440.

Every year, the Casa Verde Fotovoltaice programme helps thousands of Romanian households put solar panels on their roofs. And every year, a predictable wave of frustration follows a few weeks later: “the panels are up, so why is my bill the same?”

The answer is almost always the same. The panels are installed, but the system is not yet connected to the grid as a prosumator (prosumer — a consumer who also produces electricity). Until that happens, nothing is injected into the grid, nothing is offset against your bill, and a good part of what your system produces is simply wasted.

Full transparency before we go further: SUN WATT SRL (ANRE certificate no. 19761) is not a Casa Verde installer. We do not sell or mount panels, inverters or batteries. We handle the part that comes after — the connection dossier, the ATR, the bidirectional meter through the operator and the connection certificate — in Bucharest, Ilfov and Giurgiu. That part is what this 2026 guide is about.

How Casa Verde works, in plain terms

Casa Verde Fotovoltaice is a national financing scheme run by the AFM (Administrația Fondului pentru Mediu — the Environmental Fund Administration). Stripped of bureaucratic language, it works like this:

  • You apply for financing, in line with the AFM guide in force for the current session.
  • If accepted, the state covers a significant part of the cost of a residential photovoltaic system.
  • The system is supplied and installed by an installer validated by the AFM — you choose from the approved list.
  • The installer mounts the panels, the inverter and the related equipment, and handles the paperwork towards the AFM.

The financing amounts, eligibility rules and session calendar change between editions, so always rely on the AFM guide in force rather than last year’s forum threads.

Here is the detail that matters: the programme’s job ends, broadly speaking, when the system is installed and the AFM paperwork is settled. Connecting that system to the distribution grid as a prosumer is a separate process, with a different institution (the distribution operator), different documents and a different timeline.

The good news is that the operator treats your case as a standard one. According to the information published by Rețele Electrice România, “panels on a house that is already connected to the grid — financed from your own funds or through Casa Verde” is one of the officially listed prosumer connection scenarios, valid for installed power under 400 kW, and each scenario comes with its own dedicated application annex. In other words, you are not asking for an exception; you are following a path the operator has already mapped out.

Why the panels alone do not lower your bill

A photovoltaic system creates value in three ways:

  1. Self-consumption — you use the energy at the moment it is produced.
  2. Injection — the surplus is fed into the public grid.
  3. Offsetting — the surplus you feed in is credited against the energy you draw from the grid at night or in winter, in line with current ANRE regulations.

Without the prosumer connection, only the first mechanism works — and often only partially, because the inverter is typically configured in zero-export mode until the operator approves the connection. You cannot legally inject energy into the grid without approval, and no supplier will offset energy that is not measured by an official meter.

That official measurement is done by the bidirectional meter: a smart meter that separately records the energy you consume from the grid and the energy you feed into it. It is fitted exclusively by the distribution operator — in Bucharest, Ilfov and Giurgiu, that is Rețele Electrice România S.A. You cannot buy or fit it yourself.

The steps after installation: becoming a prosumer

Step 1: Prepare and submit the connection dossier

The dossier includes the connection application, your ID and property documents, the technical data of the system (panels, inverter), conformity certificates and the single-line diagram of the installation. We have published a detailed guide on how the prosumer connection application works if you want to see exactly what the operator expects.

This is the stage where most delays are born: an incomplete dossier means the operator requests clarifications and the clock restarts. SUN WATT prepares the complete connection dossier, design included, from 900 lei.

Step 2: Obtain the ATR

The operator analyses your request and issues the ATR (aviz tehnic de racordare — Technical Connection Approval): the document that sets out the technical solution, the approved power and the connection tariff. Nothing moves forward without it. If you already have a file in progress and just need help unblocking it, ATR assistance starts from 350 lei.

Step 3: Bring the installation in line with the ATR

The technical solution in the ATR may require adjustments on your side — protection settings, inverter parameters, sometimes works on the connection itself. Two situations come up regularly with Casa Verde systems, and we cover them below.

Step 4: The bidirectional meter

Once the dossier is approved and the installation is compliant, Rețele Electrice România S.A. fits the bidirectional meter and enables the system for injection.

Step 5: The connection certificate and the prosumer contract

The operator issues the certificat de racordare (connection certificate), the document that officially confirms your prosumer status. With it, you sign a prosumer annex or contract with your electricity supplier, and offsetting finally starts. From this point on, your Casa Verde system is doing what the brochure promised.

Who does what: a clear split of responsibilities

TaskAFM-approved installerGrid connection company (SUN WATT)
Mounting panels, inverter, structureYesNo
AFM financing paperworkYesNo
Connection dossier and designSometimes — ask!Yes, from 900 lei
ATR follow-up with the operatorSometimesYes, assistance from 350 lei
Bidirectional meterNo (operator only)Coordination with the operator
Connection certificate and supplier contractRarelyYes

The “sometimes” rows are where homeowners get burned. Some installers include the full prosumer paperwork, some submit the initial application and stop there, and some leave it entirely to you. Ask explicitly, in writing, what your contract covers — ideally before the panels go up.

Two situations that catch Casa Verde beneficiaries out

Your connection is single-phase, but the system needs three-phase

Depending on the power of the photovoltaic system, the technical solution may require a three-phase connection. If your house currently has a single-phase supply, this is additional work with its own paperwork — at SUN WATT, three-phase conversions start from 2,900 lei.

Your approved power is lower than what the system needs

The power stated in your existing connection documents may not match the new reality of a producing household. In that case you will need a power increase (spor de putere), which we handle from 350 lei.

This distinction matters more than it looks: Rețele Electrice România publishes separate scenarios — with separate annexes — for systems of up to 10.8 kW depending on whether the installed power stays within or exceeds the approved absorbed power of your existing connection. Filing under the wrong scenario is one of the small mistakes that quietly adds weeks to a Casa Verde file.

Neither situation is a catastrophe — but both add weeks if discovered late. A short technical assessment before or right after installation avoids the surprise.

How long does all of this take?

Honest answer: from a few weeks to a few months end-to-end. The variables are the completeness of the dossier, the operator’s workload, and whether your connection needs the changes described above. The formal processing terms are set out in current ANRE regulations and in the ATR itself; for orientation, the operator’s published term for evaluating the application and documentation is 10 working days, and for establishing the technical solution and issuing the ATR it is 30 calendar days — these are the terms Rețele Electrice România publishes for the standard process, not guarantees for every individual file. The practical lever you control is submitting a complete, correct dossier the first time.

The bottom line

The Casa Verde programme pays for the hardware. It does not, by itself, make you a prosumer. Between “panels on the roof” and “smaller bills” sits a bureaucratic corridor — dossier, ATR, bidirectional meter, connection certificate — that someone has to walk down.

If your installer covers it, perfect. If not, or if your file has been stuck for months, that corridor is our daily job. SUN WATT handles the complete prosumer grid connection in Bucharest, Ilfov and Giurgiu — from the first document to the moment offsetting starts — with a personalised quote based on your system and location.

Call us at 0733 097 440 and tell us where your file is stuck. We will tell you, honestly, what is missing and how long it should take.

Frequently asked questions

Does the Casa Verde programme include the prosumer grid connection?

Not automatically. The programme finances the photovoltaic system itself, and the AFM-approved installer is responsible for mounting the panels and the inverter. The grid connection as a prosumer — connection application, ATR, bidirectional meter, connection certificate — is a separate process with Rețele Electrice România S.A. Some installers offer help with the paperwork and some do not, so ask explicitly what your contract covers. If the connection side is not included, an ANRE-certified company such as SUN WATT can take it over at any point.

Can I use my solar panels before the prosumer connection is approved?

Partially. Depending on how the inverter is configured, the system may cover part of your own consumption while the sun shines. What you cannot do is legally feed surplus energy into the grid or benefit from offsetting — until the bidirectional meter is fitted and the connection certificate is issued, every kilowatt-hour of surplus is simply lost. Inverters are typically kept in zero-export mode until the operator approves the connection, which is exactly why finishing the paperwork quickly matters.

What documents do I need after the panels are installed?

The core of the prosumer dossier: your ID, the property documents for the building, the technical data sheets and conformity certificates for the panels and the inverter, the single-line wiring diagram of the installation, and the connection application itself. The operator may request clarifications or additional documents depending on the location. SUN WATT prepares the complete connection dossier, including the design part, from 900 lei, and offers ATR assistance from 350 lei if you only need help with the approval stage.

How long does it take to become a prosumer after a Casa Verde installation?

Realistically, from a few weeks to a few months, depending on how complete the dossier is, the operator's workload and whether your existing connection needs changes (for example a switch to three-phase or a power increase). For orientation, the operator's published term for establishing the technical solution and issuing the ATR is 30 calendar days, according to the information published by Rețele Electrice România — a published term for the standard process, not a guarantee for every file. In our experience, the single biggest cause of delay is an incomplete or incorrectly prepared dossier, which restarts the clock every time the operator requests corrections.

Do you install solar panels through Casa Verde?

No, and we say this openly: SUN WATT is not an AFM-approved installer and does not sell or mount panels, inverters or batteries. We are an ANRE-certified company (certificate no. 19761) specialised in the grid side: connection dossiers, the ATR, coordination with Rețele Electrice România S.A. for the bidirectional meter, and the connection certificate. If your Casa Verde installer has done their job but the paperwork is stuck, that is precisely the gap we fill, in Bucharest, Ilfov and Giurgiu.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp