Energising the connection: the final step of grid connection

In short: Energisation (punere sub tensiune) is the final step of grid connection: after the connection is built, the meter is fitted by Retele Electrice Romania S.A. and the DIU is obtained (from 1,200 lei), the installation becomes powered with electricity. The mandatory conditions are a connection built according to the design, technical acceptance, a valid DIU and a supply contract. A single-phase connection (~11 kW) starts from 1,800 lei, while a three-phase one (400V) starts from 2,900 lei, with the final price set through the ATR.

Energisation (punere sub tensiune) is the moment when your electrical installation actually receives power from the public grid. It is the final step of a process that begins with the connection request and ends with a working meter and a valid certificate (DIU). After the connection (bransament) is built, the meter is fitted by Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel, part of the PPC group) and the Utilisation Installation Dossier (DIU, from 1,200 lei) is obtained, the installation becomes powered. For a single-phase connection (~11 kW) costs start from 1,800 lei, while for a three-phase one (400V) they start from 2,900 lei, with the final price set through the ATR.

What energisation actually means

The term “energisation” (punere sub tensiune) refers to the operation through which the distribution operator connects the completed connection to the low-voltage grid and energises the customer’s electrical installation. In practice, it is the end of the road: you have already gone through the technical connection approval (ATR), the execution of the works and the technical acceptance, and now the electricity reaches your electrical panel.

Energisation is not simply a “press of a button”. It can only take place once several technical and administrative conditions have been met cumulatively. The absence of a single document — for example the DIU — blocks energisation, even if the connection is physically ready.

Who energises the connection

The distribution operator, Retele Electrice Romania S.A., is the only entity that energises the connection and fits the meter. The ANRE-certified execution company (such as SUN WATT SRL) carries out the actual connection and prepares the documentation, but the actual connection to the grid and the fitting of the metering unit remain the exclusive responsibility of the operator. This is why a complete and correct dossier, submitted in good time, significantly shortens the time until power is supplied.

The mandatory conditions for energisation

Before energisation, the following stages must be ticked off. If one is missing, the operator postpones the connection:

  • Connection built according to the design and the ATR — the works must comply with the approved technical solution (single-phase or three-phase, overhead or underground).
  • Technical acceptance of the works — verification of the conformity of the execution by the operator.
  • Valid DIU — the Utilisation Installation Dossier, drawn up by an ANRE-certified electrician/company, attests that the internal installation is safe and compliant.
  • Earthing electrode and PRAM report — measuring the dispersion resistance (PRAM, from 250 lei) confirms that the earthing electrode (from 900 lei) is working correctly.
  • Electricity supply contract — concluded with a supplier of your choice.
  • Payment of the connection charge — according to the ATR.

Only after all these elements have been validated does the operator schedule the fitting of the meter and the actual energisation.

The role of the DIU and the meter

These two elements are the heart of the final step. Without them, there is no legal power supply.

DIU — the Utilisation Installation Dossier

The DIU is the document that demonstrates that the electrical installation inside the building (from the connection cabinet (firida de bransament) to the sockets and lighting fixtures) has been carried out correctly and is safe. It is drawn up exclusively by an ANRE-certified company and includes the installation diagram, the PRAM report of the earthing electrode and the declaration of conformity. At bransam.ro we offer the complete preparation of the DIU dossier from 1,200 lei, with national validity. Without a submitted and accepted DIU, the operator does not energise the connection.

The electricity meter

The meter (the metering unit) is fitted by Retele Electrice Romania S.A. and sealed. It records consumption and is the point that delimits responsibility between the public grid and your installation. Fitting the meter and energisation are, as a rule, simultaneous operations: the operator’s technician installs the device, checks the connections and energises the connection.

The steps and indicative costs up to power supply

The table below summarises the path from the completion of the works up to energisation, with indicative prices. The final cost for grid connection is set through the ATR issued by the operator.

StageWho carries it outIndicative costResult
Single-phase connection execution (~11 kW)ANRE-certified companyfrom 1,800 leiPhysical connection built
Three-phase connection execution (400V)ANRE-certified companyfrom 2,900 leiPhysical connection built
Underground connectionANRE-certified companyfrom 3,500 leiBuried connection
Earthing electrodeANRE-certified companyfrom 900 leiProtection against electrocution
PRAM checkANRE-certified companyfrom 250 leiMeasurement report
DIU preparationANRE-certified companyfrom 1,200 leiUtilisation installation dossier
Acceptance + meter fitting + energisationRetele Electrice Romania S.A.included in connection chargeEnergised installation

For a personalised calculation, use the connection cost calculator or consult the full list of prices.

How long it takes and what can delay energisation

After the DIU and the complete documentation have been submitted, the operator schedules the visit for fitting the meter and energisation. The timeframe depends on the operator’s workload and on the correctness of the dossier. The most frequent causes of delay are:

  • An incomplete DIU or one with errors in the documentation.
  • A missing PRAM report or inadequate values of the earthing electrode.
  • A supply contract not concluded at the time of scheduling.
  • Discrepancies between the execution of the connection and the solution in the ATR.
  • A connection charge not paid in full.

For customers who urgently need power before the completion of construction, the solution is a temporary site connection (from 2,200 lei), which follows a similar energisation flow.

How bransam.ro helps you

As an ANRE-certified company for execution and design, we manage the entire chain up to energisation: connection dossier and design (from 900 lei), ATR assistance (from 350 lei), execution of the connection, the earthing electrode, the PRAM check and the preparation of the DIU. We also coordinate the relationship with Retele Electrice Romania S.A., so that energisation takes place without administrative blockages.

We operate in Bucharest, Ilfov and Giurgiu, with DIU services nationwide. If you want a quick assessment of your situation and an estimated timeframe until power is supplied, call 0733 097 440 or write to us through the contact page. We guide you step by step until your installation is energised and functional.

Frequently asked questions

Who energises the connection?

Energisation and the fitting of the meter are carried out exclusively by the distribution operator, Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel, part of the PPC group). The ANRE-certified company carries out the connection and prepares the documentation, but the actual energisation remains the responsibility of the operator.

Can I have power without a DIU?

No. The DIU (Utilisation Installation Dossier) is a mandatory condition for energisation. Without a valid DIU, drawn up by an ANRE-certified company, the operator does not fit the meter and does not energise the connection. At bransam.ro we prepare the DIU from 1,200 lei, with national validity.

How much does it cost to reach energisation?

The costs depend on the type of connection: single-phase (~11 kW) from 1,800 lei, three-phase (400V) from 2,900 lei, underground from 3,500 lei. To these are added the DIU from 1,200 lei, the earthing electrode from 900 lei and the PRAM check from 250 lei. The final price for grid connection is set through the ATR issued by the operator.

What documents are needed for energisation?

The following are needed: a connection built according to the ATR, the technical acceptance of the works, a valid DIU, the PRAM report of the earthing electrode, an electricity supply contract and proof of payment of the connection charge. The absence of any of these postpones the connection.

How long does energisation take after the DIU is submitted?

After the DIU and the complete documentation have been submitted, the operator schedules the fitting of the meter and energisation. The timeframe depends on the operator's workload and the correctness of the dossier. The most frequent delays arise due to an incomplete DIU, a missing PRAM report or a supply contract that has not been concluded.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp