Power upgrade and switching from single-phase to three-phase: when and how much it costs
If your electrical installation “trips” when you switch on several appliances at once, or if you want to install a heat pump, an EV charger or machinery, you need either a power upgrade (spor de putere) or a switch from single-phase to three-phase. This article explains the difference between the two, when they are needed, what steps they involve and how much they cost, with indicative prices from SUN WATT SRL, an ANRE-certified company for the design and execution of electrical connections (bransamente) in Bucuresti, Ilfov and Giurgiu.
What a power upgrade means and what switching to three-phase means
The two concepts are often confused, but they are not identical.
- Power upgrade (spor de putere) = increasing the approved power (kW) for your place of consumption, regardless of whether you stay on single-phase or move to three-phase. It is carried out when your current contracted power no longer covers your consumption.
- Switching from single-phase to three-phase = changing the type of supply, from a single phase (230 V) to three phases (400 V). It usually also brings a power upgrade, because three-phase allows higher power to be distributed evenly.
In short: you can request a power upgrade on single-phase (within certain limits), but above a certain threshold, the grid operator Retele Electrice Romania S.A. (formerly E-Distributie / Enel) will require you to switch to three-phase.
When you need a power upgrade
- The fuse board trips frequently when the water heater, hob, washing machine and air conditioning run simultaneously.
- You have installed, or want to install, a heat pump, photovoltaic panels with a larger inverter, or an extensive climate control system.
- The power approved in your contract (for example 5-6 kW single-phase) no longer covers your actual consumption.
When you need to switch to three-phase
- You want to install an EV charger (wallbox) of 11 kW or 22 kW, which requires three phases.
- You have machinery, motors or industrial equipment that only operate on 400 V.
- You need a higher installed power (above the usual single-phase threshold, generally around 8-11 kW, depending on the operator’s conditions).
- You are building a large house with many appliances, a workshop or a commercial space.
The steps for a power upgrade or switch to three-phase
The procedure is similar to a new connection and also goes through the distribution operator. Here are the main stages:
- Assessment and power requirements. You establish, ideally with the help of a specialist, the power you need (kW) and whether you stay on single-phase or move to three-phase.
- Preparing the grid connection (racordare) dossier. Application to Retele Electrice Romania, ownership documents, site plan, place-of-consumption data sheet. See the connection dossier service.
- Issuing the ATR (Technical Connection Approval). The operator reviews the application and issues the ATR, the document that establishes the technical solution and the final connection tariff.
- The connection contract signed with the operator, based on the ATR.
- Design and DIU. The technical documentation is prepared and, where applicable, the Utilisation Installation Dossier (DIU).
- Execution of works. Replacing the connection, fitting a new fuse board, a three-phase meter, and rewiring where needed.
- Energisation (PIF) and updating the supply contract with the new approved power.
For the dedicated steps, see the service pages for power upgrade increase and switching from single-phase to three-phase.
How much it costs: indicative prices
The total cost has two components: the connection tariff set by the operator through the ATR (variable, depending on power and distance) and the works/documentation carried out by the ANRE-certified company. Below are indicative SUN WATT SRL prices:
| Service | Indicative price (from) | Notes |
|---|---|---|
| Single-phase connection | 1,800 lei | Basic solution, lower power |
| Three-phase connection | 2,900 lei | Recommended for a large upgrade / 11-22 kW wallbox |
| Underground connection | 3,500 lei | When the grid or aesthetics require the buried option |
| Temporary site supply | 2,200 lei | Useful during construction, then made permanent |
| DIU (Utilisation Installation Dossier) | 1,200 lei | Documentation only, no labour |
| Connection dossier | 900 lei | Preparation and submission to the operator |
Important: these figures are indicative. The final price is set through the ATR, depending on the technical solution approved by Retele Electrice Romania S.A. For a quick estimate, use the connection cost calculator or check the prices page.
Practical cost examples
- Switching single-phase -> three-phase for an 11 kW wallbox: three-phase connection from 2,900 lei + connection dossier from 900 lei + DIU from 1,200 lei, plus the connection tariff from the ATR.
- Power upgrade on single-phase (without changing the phase): in many cases this only involves updating the dossier, a connection dossier from 900 lei and, possibly, minor replacements.
How long it takes
The timeframe depends on the complexity of the solution and on the operator. As a guide:
- Preparing and submitting the connection dossier: a few days.
- Issuing the ATR: generally between 30 and 90 days, in line with the regulated timeframes, depending on the power and type of connection.
- Execution and energisation after signing the contract: usually 1-3 weeks for the actual work.
With a complete and correctly prepared dossier from the start, you avoid returns and shorten the timeframes.
Single-phase vs. three-phase: which to choose
| Criterion | Single-phase (230 V) | Three-phase (400 V) |
|---|---|---|
| Usual power | up to ~8-11 kW | from ~11 kW upwards |
| 11/22 kW wallbox | no | yes |
| Large heat pump | limited | recommended |
| Consumption balancing | poorer | better |
| Initial cost | lower (from 1,800 lei) | higher (from 2,900 lei) |
If you have future plans (electric car, heat pump, workshop), switching directly to three-phase is usually more economical than two separate interventions.
Why SUN WATT SRL
- ANRE-certified for the design and execution of electrical connections.
- Coverage across Bucuresti, Ilfov and Giurgiu, plus DIU nationwide.