Technical Connection Approval (ATR): what it is, how to get it, how long it takes

In short: The Technical Connection Approval (ATR) is the document through which the distribution operator Retele Electrice Romania S.A. establishes the technical solution and the connection tariff for your electrical connection (bransament). It is issued after you submit the grid connection (racordare) request and the supporting documents, and the legal issuance period is up to 10-30 working days, depending on the type of connection. The ATR is step 2 in the process and sets the final price of the grid connection.

The Technical Connection Approval (ATR) is one of the most important documents in the process of obtaining an electrical connection (bransament). Without the ATR you cannot sign the grid connection (racordare) contract, you cannot carry out the works and you cannot energise (punere sub tensiune) the consumption point. In this guide we explain what the ATR is, what it contains, how you obtain it from Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel) and how long it takes to be issued.

What the Technical Connection Approval (ATR) is

The ATR is the official document through which the distribution operator responds to your grid connection (racordare) request. In practice, after analysing the location, the requested power and the existing electrical network in the area, the operator establishes the technical solution by which your consumption point will be connected to the distribution network and calculates the connection tariff.

The Technical Connection Approval is the moment when you find out the real price of the grid connection (the operator’s fee), separately from the cost of designing and carrying out the connection (bransament). This is why the final price of a connection cannot be guaranteed 100% before the ATR is issued. The estimates you receive at the beginning (for example, a three-phase connection from 2,900 lei labour plus materials) cover the works themselves, but not the operator’s fees that appear in the ATR.

The ATR also has a limited period of validity. If you do not sign the grid connection (racordare) contract within the stated deadline, the approval loses its validity and the process must be started again.

What an ATR contains

A Technical Connection Approval usually includes the following elements:

  • Consumption point details – address, beneficiary, request number;
  • Approved power – the maximum simultaneously absorbed power (kW) and the type of supply (single-phase or three-phase);
  • The technical connection solution – the method of connecting to the network (overhead, underground), the connection point and the length of the connection (bransament);
  • The connection tariff – the amount you pay the operator for the grid connection;
  • The technical conditions – requirements regarding the utilisation installation, the metering set, any network works;
  • The validity period – the period within which you can sign the grid connection (racordare) contract;
  • Approvals and consents required, where applicable (for example, for road or property crossings).

Based on this information, the design and the execution documentation for the connection (bransament) are then drawn up.

How to obtain the ATR: the steps

The ATR is step 2 in the complete grid connection (racordare) process. Here is how everything unfolds, from the request to energisation (punere sub tensiune).

1. Preparing the grid connection request and the documents

Before anything else, you must submit a grid connection (racordare) request accompanied by documents: identity document / company registration certificate (for businesses), proof of ownership of the land/building, urban planning certificate (where applicable), site plan and area location plan, plus a description of the utilisation installation (the requested power). This stage is part of the connection dossier that we can put together for you.

2. Submitting the request to the operator and issuing the ATR

The complete request is submitted to Retele Electrice Romania S.A.. The operator analyses the request, checks the network in the area and issues the Technical Connection Approval with the technical solution and the tariff. You can find further details about this service on the Technical Connection Approval (ATR) page.

3. Signing the grid connection contract

After you receive the ATR and agree with the solution and the tariff, you sign the grid connection (racordare) contract and pay the connection tariff to the operator.

4. Design and execution

Next comes the drawing up of the technical design and the actual execution of the connection (bransament) by an ANRE-certified company (such as SUN WATT SRL). At this stage the panel and the connection installation are also fitted.

5. The DIU dossier

After execution, the DIU Dossier (Utilisation Installation Dossier / proof of internal installation) is drawn up and submitted, confirming that the internal installation is compliant and can be safely energised.

6. Fitting the meter and energisation

Finally, the operator fits the meter and energises (punere sub tensiune) the consumption point. From here you can conclude the supply contract with an energy supplier.

Table: the connection stages and the role of the ATR

StageWhat happensWho does itIndicative duration
1. Request + documentsPreparing and submitting the connection dossierBeneficiary / certified company1-5 days
2. ATRIssuing the Technical Connection Approval (solution + tariff)Retele Electrice Romania10-30 working days
3. Connection contractSigning the contract and paying the connection tariffBeneficiary + operator1-10 days
4. Design + executionTechnical design and connection installationANRE-certified company1-4 weeks
5. DIUDrawing up and submitting the DIU DossierANRE-certified company2-7 days
6. Meter + energisingFitting the meter and energisationOperator5-15 days

The deadlines above are indicative and may vary depending on the type of connection (single-phase, three-phase, underground), the complexity of the technical solution and the operator’s workload.

How long the ATR takes to be issued

In accordance with ANRE regulations, the distribution operator has a legal deadline for issuing the ATR, which depends on the type and complexity of the grid connection. For simple connections (for example, a single-phase connection to a dwelling), the deadline is shorter; for those requiring network extensions or additional approvals, the duration increases. As a guide, we are talking about approximately 10-30 working days from the submission of a complete and correct request.

The most frequent reason for delay is an incomplete dossier or one containing errors. This is why we recommend that the documentation be prepared by an experienced company, so that you avoid returns and requests for additional information.

The price of the grid connection is made up of two distinct parts:

ComponentWhat it coversFrom (indicative)
Connection tariff (in the ATR)The fee of the operator Retele Electrice RomaniaSet through the ATR
Connection dossier / designDrawing up the technical documentation900 lei
Single-phase connection executionLabour + materials1,800 lei
Three-phase connection executionLabour + materials2,900 lei
Underground connectionLabour + materials3,500 lei
DIU DossierThe utilisation installation documentation1,200 lei

The connection tariff itself is the one communicated through the ATR and cannot be estimated exactly in advance. For an estimate of the total cost of the works you can use our connection cost calculator or you can consult the prices page.

Why you should leave the ATR to a certified company

SUN WATT SRL is an ANRE-certified company for the execution and design of electrical connections in Bucharest, Ilfov and Giurgiu, with DIU dossiers prepared throughout the country. We handle the entire process: from preparing the grid connection (racordare) request and submitting it to Retele Electrice Romania S.A., to obtaining the ATR, design, execution, DIU and right through to energisation (punere sub tensiune).

This way you avoid pointless trips, repeated additional submissions and wasted time. You call once, and we take care of the rest.

For a free assessment of your situation and an indicative estimate, contact us or call 0733 097 440.

Frequently asked questions

What is the Technical Connection Approval (ATR)?

The ATR is the official document through which the distribution operator Retele Electrice Romania S.A. establishes the technical solution for connecting your consumption point to the electrical network and calculates the connection tariff. It is step 2 in the grid connection (racordare) process and sets the final price of the operator's fee.

How long does it take to receive the ATR?

As a guide, the ATR is issued in approximately 10-30 working days from the submission of a complete and correct request, depending on the type of connection (single-phase, three-phase, underground) and the complexity of the technical solution. An incomplete dossier is the most frequent reason for delay.

What documents are needed to obtain the ATR?

As a rule, the following are needed: the grid connection (racordare) request, an identity document or company registration certificate for businesses, proof of ownership of the land or building, an urban planning certificate (where applicable), a site plan and area location plan, plus a description of the utilisation installation with the requested power. SUN WATT SRL can prepare the entire dossier for you.

How much does the ATR cost?

The connection tariff itself is set through the ATR by Retele Electrice Romania and cannot be estimated exactly in advance. Separately, drawing up the connection dossier/design starts from 900 lei, while the execution of the connection (bransament) starts from 1,800 lei (single-phase) and 2,900 lei (three-phase) respectively, for labour and materials, excluding operator fees.

Can I sign the grid connection contract without the ATR?

No. The ATR is the mandatory condition for signing the grid connection (racordare) contract. Without the approval you cannot conclude the contract, you cannot carry out the connection (bransament) and you cannot energise (punere sub tensiune) the consumption point. In addition, the ATR has a limited validity, so you must sign the contract within the stated period.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp