Technical Connection Approval: what the ATR template contains and how to read each section

In short: The Technical Connection Approval (ATR) is the document issued by Retele Electrice Romania through which the operator approves your connection to the grid. The standard template contains your identification details, the consumption point, the approved power (kW/kVA and the type of supply — single-phase or three-phase), the technical connection solution, the estimated connection tariff and the validity period (usually 12 months). Always read the approved power and the tariff first, because they determine the final cost of the electrical connection (bransament).

The Technical Connection Approval (ATR) is the document that effectively decides whether and how you connect to the electrical grid. Many clients receive the ATR from the operator, read it once and do not understand what each field means. This guide shows you what the ATR template issued by Retele Electrice Romania (formerly E-Distributie Muntenia) contains and how to read each section, so you make the right decisions before signing the connection contract.

What the Technical Connection Approval actually is

The ATR is the document through which the distribution operator approves the connection of a consumption or production point to the electrical grid. It establishes the power you can receive, the technical solution by which the electricity reaches you and how much the grid connection (racordare) costs.

The ATR is not just an informational piece of paper. It is the contractual basis on which the entire rest of the process is built: connection contract, design, electrical connection (bransament) execution, energisation (punere sub tensiune). If you want to understand the whole flow, see the dedicated technical connection approval (ATR) page.

The ATR template: the main sections

The template used by Retele Electrice Romania has a standard structure. Here are the sections you will find, in the order in which they usually appear in the document.

1. Identification details

The first section contains your name and details (or your company’s), the address and the connection request number. Check here that the name and the address of the consumption point are correct. A mistake in the address or the cadastral number can block the following steps.

2. Consumption point and location

This describes exactly where the installation is connected: the address, the cadastral number, possibly the coordinates. This section links the ATR to your property and to the physical point where the metering unit will be installed.

3. Approved power

The most important section. The operator records here:

  • the approved maximum simultaneously absorbed power (in kW);
  • the apparent power (in kVA), where applicable;
  • the type of supply: single-phase (230 V) or three-phase (400 V).

The approved power determines whether you can operate with a single-phase connection or whether you need a three-phase connection. If you request more than the value recorded here, you need a new request or a power upgrade (spor de putere).

4. The technical connection solution

This section describes how the electricity physically reaches you: the type of connection (overhead or underground), the connection point in the grid, the approximate length of the connection and the necessary equipment. Here you find out whether the connection is made from the existing grid in the area or whether it involves additional works (grid extension, transformer station).

5. The connection tariff

The ATR includes an estimated value of the connection tariff. This is the amount you pay the operator for the grid connection. Please note: the tariff in the ATR is indicative until the connection contract is signed, when it becomes the firm value.

6. The validity period

The ATR has a limited validity, usually 12 months from issue. If you do not sign the connection contract within this period, the approval loses its validity and the process must be restarted.

The final part lists the conditions you must observe: carrying out the installation in accordance with the standards, possible approvals from other grid owners, the obligation to use an ANRE-certified contractor.

Table: how to read each section of the ATR

ATR sectionWhat it containsWhy it matters to you
Identification detailsName, address, request no.Errors block the following steps
Consumption pointAddress, cadastral no.Links the approval to your property
Approved powerkW / kVA, single/three-phaseDetermines the type of connection and the cost
Connection solutionOverhead/underground, connection pointInfluences the price and duration of the work
Connection tariffEstimated amount paid to the operatorYour budget for the grid connection
ValidityUsually 12 monthsAfter expiry, you restart the process
Technical conditionsStandards, related approvals, certified contractorMandatory for energisation

Common mistakes when reading the ATR

From our experience with clients in Bucharest, Ilfov and Giurgiu, these are the most frequent points of confusion:

  • Confusing the approved power with the requested power. The operator may approve a value that differs from the one requested. Always read the approved value, not the one in the request.
  • Ignoring the validity period. Many people leave the ATR “in a drawer” and miss the 12-month deadline.
  • Believing the tariff in the ATR is the final one. The firm value appears in the connection contract.
  • Skipping over the type of supply. Single-phase or three-phase completely changes the solution and the cost. If you need to switch from one phase to three, see single-phase to three-phase conversion.

The final cost is established through the ATR and through the approved connection solution. As a guide, the usual works start from:

  • single-phase connection: from 1,800 lei;
  • three-phase connection: from 2,900 lei;
  • underground connection: from 3,500 lei;
  • connection dossier and design: from 900 lei;
  • ATR assistance: from 350 lei;
  • power upgrade: from 350 lei.

The values are indicative; the final price depends on the solution approved in the ATR. You can quickly estimate using the electrical connection cost calculator or see the full list on the prices page.

How we help you with the ATR

SUN WATT SRL is an ANRE-certified company for execution and design. We prepare the dossier and the electrical grid connection design, submit the request to the operator and provide assistance with interpreting the ATR, so that you understand the approved power, the solution and the tariff before signing the connection contract.

If you have already received an ATR and you are not sure what it means, send it to us and we will explain each section. Call 0733 097 440 or write to us through the contact page.

Conclusion

The Technical Connection Approval is the map of your grid connection: it tells you how much power you receive, how the connection is made, how much it costs and how much time you have available. Read the approved power and the tariff first, check the type of supply and do not miss the validity period. With a correct interpretation of the ATR, you avoid surprises and get connected to electricity faster.

Frequently asked questions

How long is a Technical Connection Approval valid?

The ATR usually has a validity of 12 months from the date of issue. If you do not sign the connection contract within this period, the approval loses its validity and you have to restart the process with a new connection request to the operator.

Who issues the Technical Connection Approval?

The ATR is issued by the distribution operator; in the Bucharest, Ilfov and Giurgiu area this is Retele Electrice Romania S.A. (formerly E-Distributie Muntenia, PPC group). You submit the request, and the operator analyses it and issues the approval with the approved power and the connection solution.

Is the tariff in the ATR the final price I pay?

No. The connection tariff in the ATR is an estimated value. The firm amount is established when the connection contract with the operator is signed. The cost of the electrical connection itself (the execution work) is separate and depends on the approved solution.

What do I do if the power approved in the ATR is lower than the one requested?

The operator may approve a power that differs from the one requested, depending on the capacity of the grid in the area. If you need more power, you can submit a power upgrade (spor de putere) request or you can discuss an alternative technical solution, such as extending the grid.

Do I need an ANRE-certified company for the ATR?

Yes. The design and execution of the connection installation are carried out by ANRE-certified economic operators. SUN WATT SRL is an ANRE-certified company (execution and design) that prepares the dossier and the design and provides assistance with interpreting the ATR. Call 0733 097 440.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp