Overhead Electrical Connection in Bucharest, Ilfov and Giurgiu — From 1,800 Lei

From 1,800 lei. Exact quote within 24 hours.

From 1.800 lei · exact quote within 24h

An overhead electrical connection links your property to the grid via a conductor mounted on poles, making it the fastest and most economical solution wherever poles are nearby. SUN WATT installs single-phase (230V) and three-phase (400V) overhead connections from 1,800 lei (labour plus materials, excluding operator fees), as a firm certified by ANRE (the Romanian Energy Regulatory Authority) for both design and installation. The indicative timeframe from application to energisation is around 4 to 12 weeks, and the final connection tariff is set out in the ATR (Technical Connection Approval) issued by Retele Electrice Romania (Distributie Energie Electrica Romania).

When you need it

An overhead connection is the right choice when there is an existing overhead network with poles close to your property. It is faster and cheaper than an underground connection in these cases. It suits new homes, plots being developed, and any situation where you want to avoid the digging and trenching that an underground connection requires. A single-phase connection (230V) is sufficient for typical household consumption, while a three-phase connection (400V) is recommended for high-demand equipment such as a heat pump, a workshop, or an EV charging station.

How it works — step by step

  1. Connection application and documents. We submit the connection application to Retele Electrice Romania (formerly E-Distributie Muntenia) on your behalf, together with the required documents. We work out with you the power you need and the type of overhead connection: single-phase (230V) for ordinary consumption or three-phase (400V) for high demand.
  2. Technical Connection Approval (ATR). The distribution operator reviews the application and issues the ATR (Technical Connection Approval), the document that sets out the technical connection conditions and the connection tariff. The ATR is the stage at which the overhead connection solution and the exact cost are officially confirmed.
  3. Connection contract and payment of the tariff. The connection contract is signed with the operator and the tariff set out in the ATR is paid. Only after this stage can the actual design and installation of the connection begin.
  4. Design and installation of the overhead connection. The SUN WATT team, certified by ANRE, designs and installs the overhead connection: running the conductor from the operator's pole, fitting the connection cabinet and the protection equipment, all in line with the approved design and current standards.
  5. Utilization Installation Dossier and energisation. We prepare the DIU (Utilization Installation Dossier) through an ANRE-certified electrician, after which the operator fits the meter and the supply is energised. Signing a supply contract with an energy supplier completes the connection.

Required documents

  • Owner's identity document (identity card)
  • Proof of ownership of the property or land (a recent Land Registry extract)
  • Town planning certificate (for new builds)
  • Site plan and location plan
  • Connection application (we complete this on your behalf)
  • Building permit, where applicable

Why bransam.ro

  • Turnkey service: we handle all the paperwork, from the dossier and ATR through to installing the connection and energisation
  • A firm certified by ANRE for both design and installation, so the works are accepted by the distribution operator
  • We know the Retele Electrice Romania procedures across Bucharest, Ilfov and Giurgiu, and how to avoid dossier hold-ups
  • A single point of contact for every stage, with no running back and forth between operator, designer and electrician
  • Compliant materials and equipment, correctly installed in line with safety standards
  • Honest advice on choosing between single-phase and three-phase and on sizing the contracted power

How long it takes

As a guide, the ATR is issued within a few weeks of submitting a complete dossier, and the whole journey, from application to energisation, usually takes around 4 to 12 weeks. The timeframes depend on the distribution operator, the complexity of the work, and the volume of applications during that period.

Indicative price

ServiceIndicative priceDetails
Overhead connection from 1.800 lei racord pe stâlp existent, distanță mică

Prices are indicative (labour + usual materials, excluding the Rețele Electrice România operator fees). The final price is set by the Technical Connection Approval (ATR).

FAQ — Overhead connection

How much does an overhead electrical connection cost?

Labour and materials for an overhead connection start from 1,800 lei, excluding the distribution operator's fees. On top of this comes the connection tariff, which is set individually through the ATR (Technical Connection Approval) issued by Retele Electrice Romania.

What is the difference between an overhead and an underground connection?

An overhead connection brings the electricity through a conductor mounted on poles, which is faster and cheaper where there is an overhead network in the area. An underground connection involves buried routes, trenching and, as a rule, higher costs.

Should an overhead connection be single-phase or three-phase?

For ordinary household consumption a single-phase connection (230V) is sufficient, typically up to around 11 kW approved. If you have high-demand equipment such as a heat pump, a workshop, or an EV charging station, a three-phase connection (400V) is recommended.

How long does an overhead connection take?

As a guide, the ATR is issued within a few weeks, and the whole process, from dossier to energisation, usually takes between 4 and 12 weeks.

What documents do I need for an overhead connection?

You will usually need your identity document, proof of ownership (a Land Registry extract), the town planning certificate for new builds, the site and location plans, plus the connection application.

Do you handle all the formalities, or do I have to go to the operator myself?

We handle all the paperwork. We submit the connection application, follow up on the ATR, manage the connection contract, design and install the connection, and prepare the Utilization Installation Dossier (DIU).

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp