Grid connection application: what it contains and how to complete it in 2026

In short: The grid connection application is the official form through which you request a new electrical connection (bransament) or a power upgrade (spor de putere) from the distribution operator (Retele Electrice Romania S.A., formerly E-Distributie Muntenia). It contains the applicant's details, the address of the consumption point, the requested power (kW) and the nature of the installation, accompanied by the proof of ownership, the urban planning certificate and the identity document. After submission, the operator issues the Technical Connection Approval (ATR), which establishes the technical solution and the final cost. At bransam.ro we prepare the complete dossier, with indicative prices starting from 900 lei for the dossier and connection design.

What the grid connection application is and why you need it

The grid connection application is the official document through which a consumer (individual or company) requests the distribution operator to connect a new consumption point to the electricity grid, or to modify an existing one. In the Bucharest, Ilfov and Giurgiu area, the operator is Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel, part of the PPC group).

Without a correctly completed grid connection application accompanied by the appropriate documents, the operator cannot issue the Technical Connection Approval (ATR) — the key document that establishes the technical solution, the approved power and the connection tariff. In practice, the application is the first formal step in any grid connection project.

You need a grid connection application in several situations:

  • a new electrical connection (bransament) for a building (house, warehouse, commercial space);
  • a power upgrade (spor de putere) for an existing consumption point;
  • switching from single-phase to three-phase;
  • the connection of a photovoltaic system / prosumer;
  • a temporary construction-site connection.

What the grid connection application contains

The operator’s standard form has several mandatory sections. Whether you complete it online or on paper, the structure is similar.

1. Applicant details

  • first name and surname (or the company name and tax registration number, CUI);
  • personal numeric code (CNP) / tax code;
  • home address / registered office;
  • contact details (phone, e-mail) for correspondence.

2. Consumption point details

  • the exact address where the connection is requested (street, number, village/town, county);
  • the cadastral number / land registry (carte funciara) number;
  • the intended use of the consumption point (residential, commercial, industrial, agricultural).

3. Technical details of the installation

  • the requested maximum simultaneously absorbed power, expressed in kW;
  • the desired type of supply (single-phase or three-phase);
  • the operating regime (permanent or temporary/construction site);
  • for prosumers: the installed power of the photovoltaic system and the power fed back into the grid.

4. The capacity in which the application is submitted

You must tick whether you are the owner, a tenant with the owner’s consent, a developer or an authorised representative. This section determines which supporting documents you attach.

The documents that accompany the application

The application alone is not enough. The operator requires a complete dossier. The table below summarises the usual documents, depending on the type of applicant:

DocumentIndividualLegal entityNotes
Copy of identity document / CUIYesYesID card for individuals, registration certificate for companies
Proof of ownership / right of useYesYesrecent land registry (CF) extract, contract, owner’s consent
Urban planning certificateYes (as a rule)Yesissued by the town hall for the consumption point
Site / location planYesYeswith the position of the building on the plot
Approval / building permitIf applicableIf applicablefor new buildings
Power of attorney (if applicable)OptionalOptionalif the dossier is submitted by a certified company
Technical details of the utilisation installationYesYesdrawn up by an ANRE-certified designer

In practice, the most frequent delays arise from a missing urban planning certificate or an expired land registry extract. That is why we check the entire dossier before submission.

How to complete the application step by step

  1. Determine the power you need. Under-sizing leads to frequent trips, while over-sizing needlessly increases the connection tariff. For an average home, the requested power is calculated from the sum of the consumers (boiler, hob, water heater, EV charger, etc.). You can use the connection cost calculator for an indicative estimate.

  2. Choose the type of connection. A single-phase connection covers a home with low consumption, while a three-phase connection is required for higher power, heat pumps or workshops.

  3. Complete the details exactly as in the ownership documents. Any discrepancy between the name in the application and the one in the land registry (CF) extract blocks the dossier.

  4. Attach the documents scanned legibly. The operator rejects dossiers with illegible or incomplete documents.

  5. Submit the application. According to the information published by Rețele Electrice România, the application can be submitted through an account on the operator’s online portal or at the electricity supplier’s shop. Alternatively, an ANRE-certified company can handle the entire process on your behalf.

What happens after submitting the application

After the application is registered, the operator analyses the request and issues the Technical Connection Approval (ATR). This is the document that:

  • confirms the approved power;
  • establishes the connection solution (overhead, underground, connection from the existing grid or grid extension);
  • communicates the connection tariff and the completion deadline.

The final price of the electrical connection (bransament) is always established through the ATR, not before. The figures displayed publicly are indicative. Where needed, we provide assistance in obtaining the ATR, so that the approved solution is the optimal one from both a technical and a financial point of view.

Note that the ATR reaches you only after the related invoice has been paid. From there, the operator describes the full connection process in five official steps: (1) the connection application and the issuing of the ATR, (2) the connection contract, (3) the design and execution of the works, (4) the supply contract and (5) energisation (punere sub tensiune) together with the installation of the meter. For the execution of the works, the operator’s published process lets you choose between the operator itself and an ANRE-certified firm.

For each stage, the operator also publishes official terms. Keep in mind that these are the operator’s published terms, not guarantees — the actual duration depends on the connection solution and the quality of the dossier:

StageOperator’s published term
Evaluation of the application and documentation10 working days
Establishing the solution + issuing the ATR30 calendar days
Evaluation of the contract request5 working days
Design + execution of the works90 calendar days
Acceptance (receptie) of the installation5 working days
Issuing the connection certificate3 working days
Energisation + meter installation5 working days

The cost of preparing the dossier is separate from the connection tariff set by the operator. Below are indicative bransam.ro prices:

ServiceIndicative price (from)
Dossier + connection design900 lei
ATR assistance350 lei
Single-phase connection1,800 lei
Three-phase connection2,900 lei
Underground connection3,500 lei
Power upgrade350 lei

The prices are indicative; the final value depends on the solution in the ATR. For photovoltaic systems we provide a personalised offer, because the prosumer dossier also involves the bidirectional meter installed by the operator.

Why you should leave the dossier in the hands of an ANRE-certified company

SUN WATT SRL is an ANRE-certified company for the execution and design of electrical connections (bransamente) and grid connections, covering Bucharest, Ilfov and Giurgiu. We prepare the grid connection application, the complete dossier and the design, submit the documentation to the operator and assist you all the way through to energisation. This way you avoid rejections, rework and wasted time.

Do you have a connection or power upgrade project? Call 0733 097 440 or write to us via the contact page and we will check, free of charge, which documents you need.

Frequently asked questions

How much does a grid connection application cost?

Submitting the application to the operator does not carry a significant separate cost, but preparing the complete dossier and the connection design starts, indicatively, from 900 lei at bransam.ro. The connection tariff itself is established later by the operator through the Technical Connection Approval (ATR) and depends on the approved technical solution.

What documents do I need to attach to the grid connection application?

As a rule: a copy of the identity document or tax registration number (CUI), proof of ownership or right of use (recent land registry extract), the urban planning certificate, the location plan, and for new buildings the building permit. For companies, the registration documents are added. The technical details of the installation are drawn up by an ANRE-certified designer.

Who is the distribution operator in Bucharest and Ilfov?

The distribution operator in Bucharest, Ilfov and Giurgiu is Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel, part of the PPC group). The grid connection application is submitted to this operator, and you receive the Technical Connection Approval from it.

How long does it take from the grid connection application to energisation?

After the application is submitted, the operator issues the ATR, followed by the connection contract, the execution of the works, the installation of the meter and energisation. Retele Electrice Romania publishes official terms for each stage — for example, 10 working days for evaluating the application, 30 calendar days for issuing the ATR and 90 calendar days for design and execution — but these are the operator's published terms, not guarantees, and the actual timeframes vary depending on the connection solution (overhead, underground or grid extension) and the complexity of the dossier. A certified company can shorten the process by avoiding rejections.

Can I submit a grid connection application for a photovoltaic system (prosumer)?

Yes. Connecting a photovoltaic system as a prosumer requires a grid connection application, the ATR, a compliant dossier and a bidirectional meter (smart meter) installed by the operator. SUN WATT, an ANRE-certified company, prepares the documentation and carries out the installation part. For this type of project we provide a personalised offer.

Need an electrical connection?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp