Electrical connections · Ilfov

Electrical connections in Corbeanca

SUN WATT SRL carries out single-phase (230V) and three-phase (400V) electrical connections (bransament) in Corbeanca, Ilfov county, as a firm certified by ANRE for design and execution. The grid operator in the area is Retele Electrice Romania S.A., and we prepare and submit the entire grid connection (racordare) dossier, follow up the ATR (Technical Connection Approval) and carry out the connection right through to energisation (punere sub tensiune). The indicative timescale from dossier to power at the socket is roughly 4-12 weeks, with the final tariff being set through the Technical Connection Approval (ATR).

Corbeanca is one of the top residential communes in northern Ilfov, with a character dominated by houses and villas on generous plots, spread across the villages of Tamasi, Petresti and Ostratu and the new subdivisions that have appeared along the roads towards Balotesti and Tunari. Here, the typical situation we come across is not the apartment block but the single-family home on its own land: a newly built house that still has no power, a building site that first needs a temporary connection and then the permanent one, or a household that requests a power upgrade (spor de putere) after installing a heat pump, an extended air-conditioning system or an EV charging station. On more secluded plots, the distance from the property boundary to the nearest grid pole can be greater, which is why we choose the right solution together with you - an overhead connection where there is a grid on poles nearby, or an underground one, with excavation and a protective conduit, in areas where a more discreet option is preferred. SUN WATT, a firm certified by ANRE for design and execution, covers the entire commune of Corbeanca and travels to your address to assess the position relative to the grid and the actual power requirement, recommending single-phase (230V) for ordinary household consumption or three-phase (400V) for large consumers. We handle everything, from dossier to pole: the grid connection request to Retele Electrice Romania, follow-up of the Technical Connection Approval (ATR), the contract, the design and execution of the connection, plus the Utilisation Installation Dossier (DIU) required for fitting the meter.

The distribution operator for Corbeanca is Rețele Electrice România S.A. (formerly E-Distribuție Muntenia / Enel), the body through which all connection requests are filed and the technical connection approval (ATR) is obtained, the mandatory step before any work on the network. Being a predominantly rural and residential commune, the usual solution on the plots in Tamași, Petrești, Ostratu or in the newer subdivisions remains the overhead connection from the existing pole, the more economical and faster option, although on streets where the network is buried an underground connection is also carried out. For a complete file, the operator generally requires the urban planning certificate, the proof of ownership or the land registry extract, the site plan and the connection application. As a guideline, from filing the dossier to energisation it normally takes between 4 and 12 weeks, the duration varying according to the operator and the complexity of the work.

Services available in Corbeanca

Single-phase connection

A single-phase electrical connection (230V) is the standard supply for homes with typical consumption, usually approved up to around 11 kW. SUN WATT, an ANRE-certified company, handles the entire process from start to finish, with 2026 prices starting from 1,800 lei. The timeline from file submission to energisation is typically 4-12 weeks, with the final cost confirmed through the ATR (Technical Connection Approval).

from 1.800 lei Details →

Three-phase connection

A three-phase electrical connection (400V) is needed for high consumption or powerful equipment such as heat pumps, workshops, machine tools or EV charging stations. SUN WATT, an ANRE-attested firm, handles the entire process — from the paperwork and the Technical Connection Approval (ATR) through to energisation — typically within 4 to 12 weeks. Prices start from 2,900 lei.

from 2.900 lei Details →

Temporary site connection

A temporary site connection supplies your construction site with power throughout the building works, before the permanent connection is installed. It is obtained through a connection application and a Technical Connection Approval (ATR) from Retele Electrice Romania, and is carried out by an ANRE-certified company. Prices start from 2,200 lei (labour plus materials, excluding the operator's fees), with the whole process usually taking around 4-12 weeks.

from 2.200 lei Details →

Grid connection

Electricity grid connection is the process of linking a plot, house or new premises to the electricity distribution network so you can have your own meter and power at the socket. The process involves six stages: the connection request, the Technical Connection Approval (ATR), the connection contract, the ANRE-certified service line works, the Utilization Installation Dossier (DIU) and meter installation. In Bucharest, Ilfov and Giurgiu the network operator is Retele Electrice Romania S.A. (Distributie Energie Electrica Romania). The service starts from 900 lei (labour, excluding operator fees) and typically takes 4 to 12 weeks.

from 900 lei Details →

Power increase

A power increase means raising the approved electrical power at your existing connection when your current installation can no longer cope with your consumption. It is carried out through an application to the operator Retele Electrice Romania (Distributie Energie Electrica Romania), followed by a new ATR (Technical Connection Approval), a contract and any required connection changes. In 2026, labour starts from 350 lei (excluding operator fees), with an indicative duration of 4 to 12 weeks.

from 350 lei Details →

Prosumer / solar connection

Connecting a photovoltaic system to the grid as a prosumer means submitting a connection application to Retele Electrice Romania (Distributie Energie Electrica Romania). SUN WATT, an ANRE-certified company, prepares the full dossier, obtains the ATR (Technical Connection Approval), and coordinates the installation of a bidirectional meter so you can feed your surplus energy back into the grid. The price is set through a personalised quote. Call 0733 097 440.

quote Details →

Frequently asked questions — connections in Corbeanca

Do you carry out electrical connections throughout Corbeanca, including in Tamasi, Petresti and Ostratu?

Yes. We cover the entire commune of Corbeanca and its constituent villages, including Tamasi, Petresti and Ostratu, as well as the new subdivisions in the area. We travel to your address for a free assessment, check the distance to the grid and the position of the pole, then determine whether the connection should be overhead or underground and come back to you with a clear quote. The final price is confirmed after the Technical Connection Approval (ATR) is issued by Retele Electrice Romania.

I have a new house on a more secluded plot in Corbeanca, far from the pole. Can a connection be made?

Yes. On plots in Corbeanca that are further from the grid, the solution is determined according to the position of the operator's nearest connection point. Where there is an overhead grid nearby, the overhead connection is usually the fastest option; where a more discreet solution is preferred or the grid is buried, we carry out an underground connection with excavation and a protective conduit. The distance from the grid influences the cost, which is confirmed through the ATR after the on-site assessment.

How long does the power connection take for a building in Corbeanca?

As a guide, the entire journey from submitting the dossier to energisation falls within roughly 4-12 weeks. The issuing of the Technical Connection Approval (ATR) by Retele Electrice Romania usually takes a few weeks, and the actual execution of the connection can be completed within a few days after the approvals. We prepare and submit the dossier and follow up every stage, so that you avoid delays and trips to the operator.

Need an electrical connection in Corbeanca?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp