Bolintin-Vale is one of the most dynamic towns in the north of Giurgiu county, close to the Bucharest ring road, where new residential areas and housing plots are constantly expanding. This growth brings a frequent need for electrical connections (bransament) for newly built properties, for completed houses that are still running on a construction-site power supply, or for households that want to move from a single-phase to a three-phase connection. SUN WATT SRL, a company certified by ANRE for both design and execution, covers Bolintin-Vale and the neighbouring villages and districts, handling the entire process: checking the connection possibilities, preparing and submitting the dossier to Retele Electrice Romania (formerly E-Distributie Muntenia), building the installation from the grid pole to the meter board, and preparing for energisation (punere sub tensiune). We work for individual homes, outbuildings, small guesthouses and commercial premises, tailoring the solution to the distance from the grid and the requested power, with no invented deadlines or costs until each case has been properly assessed.
For the Bolintin-Vale area, the distribution operator is Rețele Electrice România S.A. (formerly E-Distribuție Muntenia, part of the Enel group), through which all connection requests are filed and the ATR (technical connection approval) is obtained. Given its predominantly rural character and newly parcelled house plots, the usual solution is an overhead connection from an existing low-voltage network pole, the most economical option and the quickest to put in place, while on the central thoroughfares where the network is buried an underground connection can also be carried out. For a new connection, the dossier generally includes the urban planning certificate, the title deed or land registry extract, the site plan and the connection request, documents that we prepare together with the beneficiary. From the filing of the dossier to actual energisation, the indicative duration is roughly 4-12 weeks, depending on the operator's processing times and the complexity of the works.
Services available in Bolintin-Vale
Single-phase connection
A single-phase electrical connection (230V) is the standard supply for homes with typical consumption, usually approved up to around 11 kW. SUN WATT, an ANRE-certified company, handles the entire process from start to finish, with prices starting from 1,800 lei. The timeline from file submission to energisation is typically 4-12 weeks, with the final cost confirmed through the ATR (Technical Connection Approval).
Three-phase connection
A three-phase electrical connection (400V) is needed for high consumption or powerful equipment such as heat pumps, workshops, machine tools or EV charging stations. SUN WATT, an ANRE-attested firm, handles the entire process — from the paperwork and the Technical Connection Approval (ATR) through to energisation — typically within 4 to 12 weeks. Prices start from 2,900 lei.
Temporary site connection
A temporary site connection supplies your construction site with power throughout the building works, before the permanent connection is installed. It is obtained through a connection application and a Technical Connection Approval (ATR) from Retele Electrice Romania, and is carried out by an ANRE-certified company. Prices start from 2,200 lei (labour plus materials, excluding the operator's fees), with the whole process usually taking around 4-12 weeks.
Grid connection
Electricity grid connection is the process of linking a plot, house or new premises to the electricity distribution network so you can have your own meter and power at the socket. The process involves six stages: the connection request, the Technical Connection Approval (ATR), the connection contract, the ANRE-certified service line works, the Utilization Installation Dossier (DIU) and meter installation. In Bucharest, Ilfov and Giurgiu the network operator is Retele Electrice Romania S.A. (Distributie Energie Electrica Romania). The service starts from 900 lei (labour, excluding operator fees) and typically takes 4 to 12 weeks.
Power increase
A power increase means raising the approved electrical power at your existing connection when your current installation can no longer cope with your consumption. It is carried out through an application to the operator Retele Electrice Romania (Distributie Energie Electrica Romania), followed by a new ATR (Technical Connection Approval), a contract and any required connection changes. Labour starts from 350 lei (excluding operator fees), with an indicative duration of 4 to 12 weeks.
Prosumer / solar connection
Connecting a photovoltaic system to the grid as a prosumer means submitting a connection application to Retele Electrice Romania (Distributie Energie Electrica Romania). SUN WATT, an ANRE-certified company, prepares the full dossier, obtains the ATR (Technical Connection Approval), and coordinates the installation of a bidirectional meter so you can feed your surplus energy back into the grid. The price is set through a personalised quote. Call 0733 097 440.