Electrical connections · Giurgiu

Electrical connections in Crevedia Mare

SUN WATT SRL carries out single-phase (230V) and three-phase (400V) electrical connections in the commune of Crevedia Mare, Giurgiu County, as a company certified by ANRE for design and execution. The grid operator in the area is Retele Electrice Romania S.A., and the final connection charge is confirmed through the Technical Connection Approval (ATR). As a guide, from the submission of the dossier to energisation it takes approximately 4-12 weeks.

Crevedia Mare is a commune in the west of Giurgiu County, in the plain crossed by the Neajlov river, made up of several constituent villages (among them Crevedia Mare, Crevedia Mica, Dealu, Gaiseanca, Priboiu and Sfantu Gheorghe). Its rural character and scattered households mean that the typical requests are varied: a house built on a plot at the edge of the village that does not yet have a supply, the replacement of an old riser or of an old electrical connection (bransament) that can no longer cope, or the installation of a heat pump or an EV charging station, a situation in which one moves from a single-phase to a three-phase connection. SUN WATT SRL, a company certified by ANRE for design and execution, takes on the entire process in Crevedia Mare: it submits the grid connection (racordare) application with the relevant documents, follows up on the issuing of the Technical Connection Approval (ATR) by Retele Electrice Romania (formerly E-Distributie Muntenia / Enel), designs and installs the overhead or underground electrical connection, then draws up the Utilisation Installation Dossier (DIU) required for the meter. For plots located at a distance from an existing pole, we assess on site the route and any grid extension before deciding on the solution. We take you all the way to energisation (punere sub tensiune), without you having to handle the discussions with the distributor on your own.

The distribution operator for this area is Retele Electrice Romania S.A. (formerly E-Distributie Muntenia / Enel), through which all connection requests are submitted and the ATR (technical connection approval) is obtained. Being a commune made up of several component villages and scattered households, the usual solution is the overhead connection run from the existing low-voltage pole, the most economical option for this rural-type network, although in the village cores where the routes are buried underground connections or mixed situations may also occur. For a new connection, the dossier generally includes the urban planning certificate, the proof of ownership or land registry extract, the site plan and the connection request. As a guide, from the filing of the complete dossier to energisation, between 4 and 12 weeks elapse, depending on the operator's workload and the complexity of the works.

Services available in Crevedia Mare

Single-phase connection

A single-phase electrical connection (230V) is the standard supply for homes with typical consumption, usually approved up to around 11 kW. SUN WATT, an ANRE-certified company, handles the entire process from start to finish, with 2026 prices starting from 1,800 lei. The timeline from file submission to energisation is typically 4-12 weeks, with the final cost confirmed through the ATR (Technical Connection Approval).

from 1.800 lei Details →

Three-phase connection

A three-phase electrical connection (400V) is needed for high consumption or powerful equipment such as heat pumps, workshops, machine tools or EV charging stations. SUN WATT, an ANRE-attested firm, handles the entire process — from the paperwork and the Technical Connection Approval (ATR) through to energisation — typically within 4 to 12 weeks. Prices start from 2,900 lei.

from 2.900 lei Details →

Temporary site connection

A temporary site connection supplies your construction site with power throughout the building works, before the permanent connection is installed. It is obtained through a connection application and a Technical Connection Approval (ATR) from Retele Electrice Romania, and is carried out by an ANRE-certified company. Prices start from 2,200 lei (labour plus materials, excluding the operator's fees), with the whole process usually taking around 4-12 weeks.

from 2.200 lei Details →

Grid connection

Electricity grid connection is the process of linking a plot, house or new premises to the electricity distribution network so you can have your own meter and power at the socket. The process involves six stages: the connection request, the Technical Connection Approval (ATR), the connection contract, the ANRE-certified service line works, the Utilization Installation Dossier (DIU) and meter installation. In Bucharest, Ilfov and Giurgiu the network operator is Retele Electrice Romania S.A. (Distributie Energie Electrica Romania). The service starts from 900 lei (labour, excluding operator fees) and typically takes 4 to 12 weeks.

from 900 lei Details →

Power increase

A power increase means raising the approved electrical power at your existing connection when your current installation can no longer cope with your consumption. It is carried out through an application to the operator Retele Electrice Romania (Distributie Energie Electrica Romania), followed by a new ATR (Technical Connection Approval), a contract and any required connection changes. In 2026, labour starts from 350 lei (excluding operator fees), with an indicative duration of 4 to 12 weeks.

from 350 lei Details →

Prosumer / solar connection

Connecting a photovoltaic system to the grid as a prosumer means submitting a connection application to Retele Electrice Romania (Distributie Energie Electrica Romania). SUN WATT, an ANRE-certified company, prepares the full dossier, obtains the ATR (Technical Connection Approval), and coordinates the installation of a bidirectional meter so you can feed your surplus energy back into the grid. The price is set through a personalised quote. Call 0733 097 440.

quote Details →

Electrical connections across Giurgiu

Frequently asked questions — connections in Crevedia Mare

Do you carry out connections in the villages of Crevedia Mare commune?

Yes, we travel to all the constituent villages of Crevedia Mare commune, including Crevedia Mica, Dealu, Gaiseanca, Priboiu and Sfantu Gheorghe. Because the households are scattered, we first go on site to check the distance to the Retele Electrice Romania network and decide whether the electrical connection (bransament) will be overhead or underground. Call 0733 097 440 for an assessment.

What happens if my plot in Crevedia Mare is far from the grid?

On plots located at a distance from an existing pole, a grid extension or an additional pole may be needed, something that is decided by the operator Retele Electrice Romania through the Technical Connection Approval (ATR). We check on site the most suitable route and explain to you in advance how it affects the duration and cost of the works, so that there are no surprises.

What documents do I need to connect a new house in Crevedia Mare?

For a new build, you usually need an identity document, the proof of ownership (land registry extract), the urban planning certificate, the site/location plan and the grid connection (racordare) application. We check together which documents you already have and prepare the rest of the dossier so that it is accepted by the operator at the first submission.

Need an electrical connection in Crevedia Mare?

Get a free quote. We handle everything — from paperwork to the pole.

  • ✓ Free assessment & quote
  • ✓ Reply within 24h
  • ✓ ANRE-certified — execution + design
  • ✓ We handle all the paperwork
Call now WhatsApp
Message us on WhatsApp