Clejani is a commune in the north of Giurgiu county, located along the road linking the area to the A1 motorway and to the neighbouring localities, with a structure made up of several villages and a mix of older households and buildings put up in recent years. In areas like this, the most frequent requests come from owners of new houses who need an electrical connection (bransament) for the first time, from those building a house on extra-urban land only recently brought into residential use, or from families wishing to separate a dwelling into a second connection. Added to these are requests for site-setup connections, increasing the contracted power (spor de putere) when heat pumps, electrical boilers or air-conditioning units are installed, or replacing old installations that can no longer cope with current consumption. SUN WATT SRL, a company certified by ANRE for both design and execution, travels to Clejani and to its constituent villages for on-site assessment, the preparation of technical documentation and the completion of grid connection (racordare) works in coordination with the operator Retele Electrice Romania. We cover the entire commune and the surrounding areas of Giurgiu, so that distance from Bucharest or from the town of Giurgiu is no obstacle to correct and compliant work.
The distribution operator for Clejani is Rețele Electrice România S.A. (formerly E-Distribuție Muntenia, part of the Enel group), through which all connection requests are submitted and the ATR (technical connection approval) is issued. As a rural commune with households spread along the main roads, the usual and also most economical solution remains the overhead connection, made from the existing pole of the low-voltage network located near the property, with the buried variant appearing only occasionally, where the local layout requires it. For a new connection one typically prepares the urban planning certificate (certificat de urbanism), the title deed or land registry extract, the site plan and the connection application, documents on the basis of which the dossier is reviewed. From the complete filing of the dossier until the actual energisation, the indicative duration falls within 4-12 weeks, depending on the operator's workload and the complexity of the work.
Services available in Clejani
Single-phase connection
A single-phase electrical connection (230V) is the standard supply for homes with typical consumption, usually approved up to around 11 kW. SUN WATT, an ANRE-certified company, handles the entire process from start to finish, with 2026 prices starting from 1,800 lei. The timeline from file submission to energisation is typically 4-12 weeks, with the final cost confirmed through the ATR (Technical Connection Approval).
Three-phase connection
A three-phase electrical connection (400V) is needed for high consumption or powerful equipment such as heat pumps, workshops, machine tools or EV charging stations. SUN WATT, an ANRE-attested firm, handles the entire process — from the paperwork and the Technical Connection Approval (ATR) through to energisation — typically within 4 to 12 weeks. Prices start from 2,900 lei.
Temporary site connection
A temporary site connection supplies your construction site with power throughout the building works, before the permanent connection is installed. It is obtained through a connection application and a Technical Connection Approval (ATR) from Retele Electrice Romania, and is carried out by an ANRE-certified company. Prices start from 2,200 lei (labour plus materials, excluding the operator's fees), with the whole process usually taking around 4-12 weeks.
Grid connection
Electricity grid connection is the process of linking a plot, house or new premises to the electricity distribution network so you can have your own meter and power at the socket. The process involves six stages: the connection request, the Technical Connection Approval (ATR), the connection contract, the ANRE-certified service line works, the Utilization Installation Dossier (DIU) and meter installation. In Bucharest, Ilfov and Giurgiu the network operator is Retele Electrice Romania S.A. (Distributie Energie Electrica Romania). The service starts from 900 lei (labour, excluding operator fees) and typically takes 4 to 12 weeks.
Power increase
A power increase means raising the approved electrical power at your existing connection when your current installation can no longer cope with your consumption. It is carried out through an application to the operator Retele Electrice Romania (Distributie Energie Electrica Romania), followed by a new ATR (Technical Connection Approval), a contract and any required connection changes. In 2026, labour starts from 350 lei (excluding operator fees), with an indicative duration of 4 to 12 weeks.
Prosumer / solar connection
Connecting a photovoltaic system to the grid as a prosumer means submitting a connection application to Retele Electrice Romania (Distributie Energie Electrica Romania). SUN WATT, an ANRE-certified company, prepares the full dossier, obtains the ATR (Technical Connection Approval), and coordinates the installation of a bidirectional meter so you can feed your surplus energy back into the grid. The price is set through a personalised quote. Call 0733 097 440.