Stoenești is a commune in the north of Giurgiu County, located near Bucharest and the Ilfov area, with rural-type villages where new houses are constantly being built and existing households are being modernised. For those putting up a home on land with no power supply, or who want to move from an old single-phase connection to a three-phase one for pumps, electric boilers or higher-power tools, a new electrical connection (bransament) is required, correctly sized and approved by the distribution operator. SUN WATT SRL covers the entire commune of Stoenești and travels on site to assess the distance to the existing grid, the position of the pole and the appropriate connection solution. As a company certified by ANRE for both design and execution, we prepare the technical documentation, submit the grid connection (racordare) request to Retele Electrice Romania S.A. and carry out the works from the connection cabinet (firida de bransament) through to the electrical panel, so that the owner in Stoenești does not have to coordinate several suppliers. We treat each situation according to the specifics of the land and the client's real needs, without unrealistic promises about timeframes that depend on the operator.
All connection requests and the issuance of the technical connection approval (ATR) are handled by the area distribution operator, Rețele Electrice România S.A. (formerly E-Distribuție Muntenia / Enel), which sets the technical solution and the delimitation point. As a locality with a rural profile, in the commune's villages the connection is most often made overhead, by a drop from the low-voltage pole near the property, a faster and more economical option than the underground network; where buried network sections exist, an underground connection can also be chosen. For a new connection you usually prepare the urban planning certificate, the property deed or land registry extract, the site plan and the connection request. As a guideline, between 4 and 12 weeks pass from filing the complete dossier to energisation, depending on the operator's workload and the complexity of the works.
Services available in Stoenești
Single-phase connection
A single-phase electrical connection (230V) is the standard supply for homes with typical consumption, usually approved up to around 11 kW. SUN WATT, an ANRE-certified company, handles the entire process from start to finish, with 2026 prices starting from 1,800 lei. The timeline from file submission to energisation is typically 4-12 weeks, with the final cost confirmed through the ATR (Technical Connection Approval).
Three-phase connection
A three-phase electrical connection (400V) is needed for high consumption or powerful equipment such as heat pumps, workshops, machine tools or EV charging stations. SUN WATT, an ANRE-attested firm, handles the entire process — from the paperwork and the Technical Connection Approval (ATR) through to energisation — typically within 4 to 12 weeks. Prices start from 2,900 lei.
Temporary site connection
A temporary site connection supplies your construction site with power throughout the building works, before the permanent connection is installed. It is obtained through a connection application and a Technical Connection Approval (ATR) from Retele Electrice Romania, and is carried out by an ANRE-certified company. Prices start from 2,200 lei (labour plus materials, excluding the operator's fees), with the whole process usually taking around 4-12 weeks.
Grid connection
Electricity grid connection is the process of linking a plot, house or new premises to the electricity distribution network so you can have your own meter and power at the socket. The process involves six stages: the connection request, the Technical Connection Approval (ATR), the connection contract, the ANRE-certified service line works, the Utilization Installation Dossier (DIU) and meter installation. In Bucharest, Ilfov and Giurgiu the network operator is Retele Electrice Romania S.A. (Distributie Energie Electrica Romania). The service starts from 900 lei (labour, excluding operator fees) and typically takes 4 to 12 weeks.
Power increase
A power increase means raising the approved electrical power at your existing connection when your current installation can no longer cope with your consumption. It is carried out through an application to the operator Retele Electrice Romania (Distributie Energie Electrica Romania), followed by a new ATR (Technical Connection Approval), a contract and any required connection changes. In 2026, labour starts from 350 lei (excluding operator fees), with an indicative duration of 4 to 12 weeks.
Prosumer / solar connection
Connecting a photovoltaic system to the grid as a prosumer means submitting a connection application to Retele Electrice Romania (Distributie Energie Electrica Romania). SUN WATT, an ANRE-certified company, prepares the full dossier, obtains the ATR (Technical Connection Approval), and coordinates the installation of a bidirectional meter so you can feed your surplus energy back into the grid. The price is set through a personalised quote. Call 0733 097 440.